The Langchao integrated big data center project (Phase I) has successfully passed the comprehensive acceptance and is expected to be officially put into operation in the second half of the year.
The Langchao Integrated Big Data Center project is located in Zhangjin Comprehensive Bonded Zone, Jinan City, Shandong Province, with a total investment of about 8 billion yuan. By introducing green energy-saving technology, the PUE is less than 1.25, reaching the leading level in China. The total construction area of the first phase of the project is about 23000 square meters.

According to the consulting and design information, the Inspur Integrated Big Data Center Park plans to construct 4 data centers, 4 power centers, 1 110kV substation, and related supporting facilities, providing more than 8000 cabinets. The project will be implemented in stages.
At the end of October last year, the main structure of the first phase of the Inspur Integrated Big Data Center project was capped. After the project passed the completion acceptance recently, it is expected to be officially put into operation in the second half of the year.

Park planning
In March of this year, the bidding for the second phase of the project was launched and the design plan was publicly announced. According to Shandong Provincial Postal and Telecommunications Planning and Design Institute, the second phase project plans and designs three data centers, three power centers, and one 110kV substation, covering all professional designs such as civil engineering and process engineering.